Timeline

Timeline

MVC1 timeline is pending updates.

August 2024
MVC1 Planning Starts
March 2025
MVC2A and 2B Planning Starts
June 2025
MVC1 Site Surveys Initiated
May 2026
MVC1 Site Implementation Begins
September 2026
MVC1 Transition Complete
October 2026
MVC2A Site Surveys Initiated
2nd - 6th November 2026
MVC2A Train the Trainer
November 2026
MVC3 & FOC Planning Starts
19th - 25th January 2026
MVC2A Train the User
February 2027
MVC2A Site Implementation Begins
TBD
MVC2B Site Surveys Initiated
April 2027
MVC2B Train the Trainer
TBD
MVC2B Train the User
July 2027
MVC2B Site Implementation Begins
October 2027
MVC2A Transition Complete
TBD
MVC3 & FOC Site Surveys Initiated
TBD
MVC3 & FOC Train the Trainer
TBD
MVC3 & FOC Train the User
March 2028
MVC3 Site Implementation Begins
April 2028
MVC2B Transition Complete
May 2028
FOC Site Implementation Begins
September 2028
MVC3 & FOC Transition Complete
September 2028
Full Transition to LogiCole Complete
August 2024
MVC1 Planning Starts
March 2025
MVC2A and 2B Planning Starts
June 2025
MVC1 Site Surveys Initiated
May 2026
MVC1 Site Implementation Begins
September 2026
MVC1 Transition Complete
October 2026
MVC2A Site Surveys Initiated
2nd - 6th November 2026
MVC2A Train the Trainer
November 2026
MVC3 & FOC Planning Starts
19th - 25th January 2026
MVC2A Train the User
February 2027
MVC2A Site Implementation Begins
TBD
MVC2B Site Surveys Initiated
April 2027
MVC2B Train the Trainer
TBD
MVC2B Train the User
July 2027
MVC2B Site Implementation Begins
October 2027
MVC2A Transition Complete
TBD
MVC3 & FOC Site Surveys Initiated
TBD
MVC3 & FOC Train the Trainer
TBD
MVC3 & FOC Train the User
March 2028
MVC3 Site Implementation Begins
April 2028
MVC2B Transition Complete
May 2028
FOC Site Implementation Begins
September 2028
MVC3 & FOC Transition Complete
September 2028
Full Transition to LogiCole Complete
August 2024
MVC1 Planning Starts
March 2025
MVC2A and 2B Planning Starts
June 2025
MVC1 Site Surveys Initiated
May 2026
MVC1 Site Implementation Begins
September 2026
MVC1 Transition Complete
October 2026
MVC2A Site Surveys Initiated
2nd - 6th November 2026
MVC2A Train the Trainer
November 2026
MVC3 & FOC Planning Starts
19th - 25th January 2026
MVC2A Train the User
February 2027
MVC2A Site Implementation Begins
TBD
MVC2B Site Surveys Initiated
April 2027
MVC2B Train the Trainer
TBD
MVC2B Train the User
July 2027
MVC2B Site Implementation Begins
October 2027
MVC2A Transition Complete
TBD
MVC3 & FOC Site Surveys Initiated
TBD
MVC3 & FOC Train the Trainer
TBD
MVC3 & FOC Train the User
March 2028
MVC3 Site Implementation Begins
April 2028
MVC2B Transition Complete
May 2028
FOC Site Implementation Begins
September 2028
MVC3 & FOC Transition Complete
September 2028
Full Transition to LogiCole Complete

*This reflects estimated milestones and may be updated as development progresses.

MVC 2A Site Rollout Schedule and ICAM Registration Information

Check out the rollout schedule posted on the MEDLOG IT Resource Center (MIRC) and Veterans Affairs Resource Center (VARC) so you can see when your site is scheduled to receive LogiCole’s Customer Ordering and Inventory Management capability. You can search by site name or DoDAAC. Users must be registered in ICAM prior to their site receiving MVC 2A capabilities.

For instructions on how to register for ICAM visit:

MVC 2A Site Rollout Schedule and ICAM Registration Information

Check out the rollout schedule posted on the MEDLOG IT Resource Center (MIRC) and Veterans Affairs Resource Center (VARC) so you can see when your site is scheduled to receive LogiCole’s Customer Ordering and Inventory Management capability. You can search by site name or DoDAAC. Users must be registered in ICAM prior to their site receiving MVC 2A capabilities.

For instructions on how to register for ICAM visit:

MVC1 Site Rollout Schedule and ICAM Registration Information

Check out the rollout schedule posted on the MEDLOG IT Resource Center (MIRC) and Veterans Affairs Resource Center (VARC) so you can see when your site is scheduled to receive LogiCole’s Customer Ordering and Inventory Management capability. You can search by site name or DoDAAC. Users must be registered in ICAM prior to their site receiving MVC1 capabilities.

For instructions on how to register for ICAM visit:

MVC1 Site Rollout Schedule and ICAM Registration Information

Check out the rollout schedule posted on the MEDLOG IT Resource Center (MIRC) and Veterans Affairs Resource Center (VARC) so you can see when your site is scheduled to receive LogiCole’s Customer Ordering and Inventory Management capability. You can search by site name or DoDAAC. Users must be registered in ICAM prior to their site receiving MVC1 capabilities.

For instructions on how to register for ICAM visit: